Phase 2 – Overhead Utility Relocation:
JCP&L is nearing completion of their utility relocation work. The communication utilities have been notified to relocate their lines to the new poles and remove the old poles, however, at this time, there is no schedule for completion of the utility work.
Phase 3 – Bridge Replacement:
Timing for the start of bridge construction is dependent on the completion of the utility work, the temperature/weather conditions, the general contractor’s work schedule, as well as any other unforeseen conditions. A preliminary bridge construction schedule will be developed once the utility work is completed.
Main Street at Bridge Q-06 remains open to traffic. The 10-ton weight posting remains in effect.