Main Street Bridge Q-06 Replacement Project (update)

Phase 2 – Overhead Utility Relocation:

JCP&L is nearing completion of their utility relocation work. The communication utilities have been notified to relocate their lines to the new poles and remove the old poles, however, at this time, there is no schedule for completion of the utility work.   

Phase 3 – Bridge Replacement:

Timing for the start of bridge construction is dependent on the completion of the utility work, the temperature/weather conditions, the general contractor’s work schedule, as well as any other unforeseen conditions. A preliminary bridge construction schedule will be developed once the utility work is completed.

Main Street at Bridge Q-06 remains open to traffic. The 10-ton weight posting remains in effect.

Additional Info...
Facebook Twitter Email

Other News in Home

Dean Blumetti presented with the ANJEC Environmental Leadership Award

Municipal Leadership Award

Posted on: November 1, 2023

Free COVID 19 test kits available.

Posted on: October 17, 2023

2023 RESIDENTIAL LEAF BAG COLLECTION

Posted on: September 29, 2023

Stay connected!

Posted on: November 22, 2016

Website Personalization Now Available!

Posted on: November 22, 2016

Keep in Touch

Posted on: November 22, 2016